Wisconsin Moratoria
Every infrastructure moratorium we have identified in Wisconsin as of April 2026.
2 instruments — 2 in force, 0 pending, 0 past. Activity level: Medium.
| Jurisdiction | Type | Date enacted | Duration | Status |
|---|---|---|---|---|
| City of Madison | City | 2026-01-24 | One year, or until earlier adoption of data center ordinance amendments | 🟡 Pending |
| Manitowoc County | County | 2026-04-28 | 18 months per WBAY contemporaneous reporting after the 2026-04-28 board vote; co | 🟡 Pending |
Detailed entries
City of Madison
- Type: City
- Status: 🟡 Pending
- Date enacted: 2026-01-24
- Duration: One year, or until earlier adoption of data center ordinance amendments
- Moratorium ID:
wi-madison-2026 - Legal basis: Legistar File 91135, Ordinance ORD-26-00002, creating MGO Sec. 28.140
- What prompted it: Madison cited the absence of a data center definition or specific standards in MGO Chapter 28. The city also identified potential energy, water, emergency service, traffic, noise, air quality, fiscal, and land use impacts
- Affected projects: New principal-use data centers and telecommunications centers over 10,000 sq ft requiring zoning certificates in Madison
- Detailed status: Active
- Outcome: Pending. The moratorium gives city agencies time to draft a permanent definition and zoning standards
Manitowoc County
- Type: County
- Status: 🟡 Pending
- Date enacted: 2026-04-28
- Duration: 18 months per WBAY contemporaneous reporting after the 2026-04-28 board vote; co
- Moratorium ID:
wi-manitowoc-county-2026 - Legal basis: Ordinance 2026/2028-10, creating Manitowoc County Code Sec. 8.495
- What prompted it: Town petitions from Mishicot, Two Creeks, and Two Rivers; concerns about health and safety, air quality, water resources, water use, electricity demand, fire hazards, public services, roads, property values, noise, visual impacts, farmland preservation, and lack of county data center standards
- Affected projects: Data centers in county-zoned areas, especially Mishicot, Two Creeks, and Two Rivers. Reporting identifies Cloverleaf Infrastructure land outreach in the area, but no filed project application was identified
- Detailed status: Approved by county board on 2026-04-28; active upon publication
- Outcome: Pending. The county plans to study impacts and develop zoning and regulatory standards
Source: moratorium_inventory.csv · Methodology · Codebook.